Project Timeline

555 TENTH AVENUE

OVERVIEW     ARCHITECTURE & DESIGN     FINANCING     LOCATION

PHOTO GALLERY     TIMELINE     CONSTRUCTION UPDATE

SEPTEMBER Building 100% Occupied
JUNE Building 75% Occupied
2017 APRIL Project Substantially Complete
OCTOBER First Tenant Move-ins
SEPTEMBER Receive first City-Awarded Temporary Certificate of Occupancy
AUGUST Begin Punchlist Program to ensure quality control of finishes, fixtures, and equipment in the building
MAY Curtain wall substantially complete
FEBRUARY Curtain wall panels have been installed on 49 Floors
2016 JANUARY Curtain wall panels have been installed on 48 Floors
DECEMBER Curtain wall panels have been installed on 45 Floors
NOVEMBER Curtain wall panels have been installed on 41 Floors. Crane is removed from the site
OCTOBER Curtain wall panels have been installed on 34 Floors
SEPTEMBER Curtain wall panels have been installed on 27 Floors
AUGUST Completed the 52nd Floor. Curtain wall panels have been installed on 24 Floors
JULY Completed Floors 44 through 51
Begin Interior Construction
JUNE
Floors 35 through 43 completed
MAY
Floors 27 through 34 completed
APRIL Finished working on Floors 16 through 26 Commence Building Enclosure
MARCH Completed Floors 10 through 15
Construction Loan Closed
FEBRUARY
Completed the 9th Floor Mezzanine and started working on the 10th Floor
2015 JANUARY
Started working on the 9th Floor
DECEMBER
Completed the 6th, 7th & 8th Floors
NOVEMBER Signed GMP with Gotham Construction Completed the 4th Floor and started working on the 5th Floor deck
OCTOBER Set up Construction Crane
SEPTEMBER Complete Foundation work and Begin Vertical Construction
2014 JULY Finalize Contract with General Contractor
SEPTEMBER Demolition and Foundation Work Commenced
2013 AUGUST Received Permits for Foundation
2012 JULY Developer Purchased Air Rights from Adjacent Site
2011 AUGUST Entered Ground Lease